Eielson AFB Cable Plant Design and Installation
Fairbanks, AK | Avaya

Cable infrastructure design for Eielson Air Force Base.
Scope of Work
After government approvals, construction and installation was conducted during the warm months (after ground thaw), which includes: 6 manholes; 96 handholes; 40,816 feet of trenching; 8,771 feet of directional boring; 87,426 feet of PVC duct; 19,394 feet of HDPE duct; fabric inner-duct; and 295,575 feet of fiber cable. MasTec's previous experience working in Alaska allowed us to overcome challenges inherent in this cold weather environment.
Services Employed
- Design, engineering, installation, integration, and turn-up
- Trenching and directional boring
- Testing
- Project Management